![]() |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
![]() |
UNIFORMAT II enables superior building design management with all project stakeholders communicating effectively, using and sharing the same project elemental cost estimate data. This building design article appeared in the May 1998 issue of "THE PROJECT MANAGER." It's about improving building project management through better project team communications, coordination and productivity with the ASTM UNIFORMAT II Standard. The author is Robert P. Charette, PE, CVS, who was co-chairman of the ASTM Task Group that developed UNIFORMAT II. He presents seminars on a regular basis on UNIFORMAT II, Life Cycle Costing, and Value Engineering. AbstractThis article, which appeared in the May 1998 issue of "THE PROJECT MANAGER," is about improving building project management through better project team communications, coordination and productivity with the ASTM UNIFORMAT II Standard Classification for Building Elements and Related Sitework. It explains how UNIFORMAT II is used as a common structure to link schematic phase Preliminary Project Descriptions (PPD), described in CSI Practice FF/180, to elemental design estimates. This approach provides the technical and cost information necessary to initiate life cycle costing, energy analysis, and value engineering studies during the initial phase of the design process, i.e. schematic design. Building design management team members at this time are receptive to alternatives that provide better value because design changes can be made at little or no cost, and potential savings are greater than at the following design development phase. Lack of design and cost information is always one of the major obstacles to the effective introduction of life cycle costing, energy analysis, and value engineering early in the design process, a problem that can be resolved with UNIFORMAT II. Furthermore, it allows input, at the schematic phase, from: (1) the facility programmer and users, who can comment as to whether or not program functional requirements are satisfied, (2) the construction manager, who can advise on constructability earlier than usual, and (3) the facility manager, who can advise on acceptable building systems with competitive operating and maintenance costs. The project benefits from their expertise at a time when design decisions are not frozen and suggestions can be seriously considered in a constructive exchange of views, without the confrontation that would occur if they were proposed in the final stages of design. The article should be of interest to all stakeholders in a building project, i.e. owners, project and construction managers, cost managers, designers, value engineers, energy analysts, life cycle costing analysts, facility managers and users. - everyone on the building design management team.
The ProblemProject managers face two major problems during the design phase that have a significant impact on the building design management team performance:
The SolutionTo resolve these problems, two relatively new tools are available to project managers:
Their integration into the design process results in:
ASTM Standard E1557 UNIFORMAT IIASTM E1557, UNIFORMAT II, defines a standard classification for building elements and related sitework. The classification was the direct responsibility of Subcommittee E-06.81 on Building Economics, and it is the only such standard in North America. (See Figure 1 - Classification Of Building Elements and Figure 2 - Classification Of Building Related Sitework). The original UNIFORMAT was developed jointly by the General Services Administration (GSA) and the American Institute of Architects (AIA) in 1972 for estimating and design cost analysis. UNIFORMAT II, first issued by ASTM in 1993, is an enhanced version developed by a task group that included amongst others CSI, GSA, AACE, the Tri-Services, R.S. Means and CIQS. It is more comprehensive than the original, particularly with respect to the mechanical and sitework elements. Thus the format is suitable for numerous other applications, such as Schematic Phase PPD. Elements are traditionally defined as "major components, common to most buildings, that perform a given function, regardless of the design specification, construction method, or materials used." In practice, an element may be considered any logical component of a Work Breakdown Structure (WBS). From a project management perspective, the UNIFORMAT II classification is the ideal WBS for the design phase of a building project to control scope, cost, quality, and time.
CSI Practice FF/180 Elemental PPDsThe basic principles of Preliminary Project Descriptions and Outline Specifications are set out in CSI Practice FF/180. According to the practice, a PPD should be structured according to the UNIFORMAT classification rather than MASTERFORMAT, based on the fact that design information at the Schematic Phase may be communicated more effectively by building functional elements. Information is also more easily understood by clients and others who do not have a technical background. For the Design Development Phase, the practice suggests an "Outline Specification", organized according to MASTERFORMAT (Divisions 1-16). In practice, the elemental format could also be used for this phase by the addition of more detailed design information to the description of each element, thus improving the building design management process. A Preliminary Project Description example from the CSI Manual of Practice is shown in Figure 3 - Elemental Preliminary Project Description. Note that the language is simple, no more technical than necessary, and meant to be easily understood by all building design management team members, design professionals as well laymen.
Using UNIFORMAT II at the Schematic and Design Development Phases has the following advantages:
If the design as described in the PPD is within project scope and budget, the designers can proceed from the Schematic Phase to the Design Development Phase with the assurance that most major outstanding issues have been resolved or identified, the building design management team clearly understands the scope of work, and the client has signed off on the PPD. This means fewer subsequent changes and a more efficient building design management process. Software for both Preliminary Project Descriptions and Outline Specifications is available commercially for under $275 (sources are listed at the end of this article.)
UNIFORMAT II Elemental EstimatesElemental estimates differ from trade estimates in that they are based on a building systems/assemblies classification (UNIFORMAT II) in lieu of a product classification (CSI MASTERFORMAT Divisions 1-16). For example, in a conventional trade estimate, all components of an exterior wall such as the brick, vapor retarder, insulation and block back-up would be priced separately, distributed in their respective divisions, and their cost summarized with all other products, according to Divisions 1-16, usually with no indication as to their construction function, i.e. for foundations, walls or partitions. With the elemental approach, the description, quantity and cost of the Exterior Wall B2010 would be identified separately, thus greatly facilitating cost analysis. Figure 5 - Means Assemblies Cost Data is an example of a composite cost for element B2010, Exterior Walls. For other projects with similar walls, the unit cost shown of $ 20.40 per SF can be used for a relatively accurate early design estimates, thus saving a great deal of time. Unit costs for most UNIFORMAT II elements, including mechanical and electrical, can be found in the Means Assemblies Cost Data Manual.
A UNIFORMAT II elemental estimate cost summary for a 54,000 SF office building is presented in Figure 4 - Building Elemental Cost Summary. It differs from a MASTERFORMAT product or trade based Divisions 1-16 estimate summary in that numerous analytic parameters and ratios are generated that facilitate design cost analysis and the monitoring of costs from the design program phase through completion of the Construction Documents Phase. For example, the average cost of partitions, (C1010) from the elemental estimate is $3.46/ SF. The partition density (the ratio of the quantity of partitions per square foot GFA) is 1.27. Partitions represent 4.39% of total cost. Extracting such data for analysis from MASTERFORMAT Division 1-16 estimates would be extremely time consuming and costly. A standardized cost reporting format based on UNIFORMAT II, such as shown in Figure 4 - Building Elemental Cost Summary, has the added advantage of facilitating the rapid reconciliation of estimates from different sources; this is because all design and inflation contingencies, and overhead and profit can be calculated in the same way, a rare occurrence when comparing design estimates in today's context.
Using the UNIFORMAT II classification to structure design estimates has numerous other advantages in the building design management process, including the following:
Other UNIFORMAT II ApplicationsThe classification has other practical applications in planning, design, construction, and facilities management that standardize reporting and link all phases of a building life cycle, improving the overall building design management process. Some of the applications include:
It should be noted that:
Benefits of Elemental Specifications and EstimatesAll building design management team members, including the client and user, benefit from a structured, standardized approach to elemental PPD and design estimates based on UNIFORMAT II. Some of these benefits include the following:
Implementing UNIFORMAT IITo implement UNIFORMAT II effectively for building design management, written directives or guidelines must be issued to each team member; a briefing session for the team should be held prior to the start of design to ensure that everyone clearly understands the procedures to be followed and the resulting benefits for all participants. The directives should include ASTM Standard EE1557lement definitions, CSI Practice FF/180 and examples of both elemental estimates and specifications. Special instructions from the project manager pertaining to specifications and estimates should also be included in the directives. The implementation of UNIFORMAT II during design must be planned by the project manager with the consultants to avoid any potential roadblocks. The first projects could be viewed as pilot projects and additional design fees possibly considered to encourage everyones collaboration in view of the anticipated benefits. Ideally, the requirement for the use of UNIFORMAT II for the preparation of PPD and estimates should be incorporated in the consultant RFP and contract documents. As a result of improved team communications and coordination, the project manager can have more time to address other important issues, and manage the project to a successful completion with less effort than normally required.
ConclusionsThere is a need in North America to improve communications and coordination during the design of buildings. Doing so results in economic benefits to the construction industry as a whole. Project managers and clients can support this objective and benefit from standardizing PPD and design estimates based on two key building design management tools, the ASTM UNIFORMAT II Standard Classification E1557 and CSI Practice FF/180. Additional information on UNIFORMAT II is provided in the resources that follow.
Building Design Management ResourcesElemental Preliminary Project Descriptions
Outline Specifications
UNIFORMAT Building Design Management References
Copies of the articles "UNIFORMAT II for Estimating and Design Cost Analysis" and "Increase VE Team Performance with UNIFORMAT II" may be obtained from the author.
The AuthorRobert P. Charette, PE, CVS was co-chairman of the ASTM Task Group that developed UNIFORMAT II. He presents seminars on a regular basis on UNIFORMAT II, Life Cycle Costing, and Value Engineering at the McGill University School of Architecture Design & Modelling Centre. He may be reached by telephone or fax at 514-739-3522 or by e-mail at charette@uniformat.com. Return to the home page from
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||